Organisation and Project Management of a Major Industrial Engineering
and Construction Project
by Gianluca di Castri
Key words
Abstract
With reference to a petrochemical
complex in Asia, this paper explains how companies working together on
a project are organised and how they interface with each other.
In this case, the organisations involved were:
-
the Owner, as Employer as well as User of the
plant,
-
the Project Managing Contractor, whose
structure was strictly cooperating with some offices of the Owner,
since the PMC was also in charge of the training of the personnel
belonging to some departments of the Owner itself,
-
the Engineering Contractors, whose tasks were
engineering, procurement, supervision of the construction and startup
of the plant,
-
the Construction Contractors and
-
the Civil Contractors (office buildings and
other ancillary buildings, roads, railway connection, etc.)
dr. ing. Gianluca di Castri, FwAICE CCE/ICECA
Ingegnere Meccanico
Esperto in Ingegneria Economica
via Don Minzoni, 11
I-20060 Pozzo d'Adda Mi
Italy
Delegato dell’AICE
presso l’ICEC
Tel. + 39 34 8272 7671
Fax + 39 02 9096 0694
E-mail:
gdicastri@uli.it
Organisation and Project Management of a
Major Industrial Engineering and Construction Project
1. General
This paper aims at describing the organisation and
project management of a major engineering and construction project.
Reference is made to a real case.
We shall demonstrate that, in complex projects, it
is not enough to consider separately the organisation of each
Contractor, while it is most important to study how the various
organisations interact each other in order to create a single,
multiple and complex organisation to run the construction site.
2. The referred project
2.1 Main data
The project referred to was relevant to the
engineering and construction of a major, integrated petrochemical
plant in an extra-European country, whose development was at a medium
level and whose economic system was mixed. In this country, the oil
and petrochemical sector was part of the planned, centralised and
state-owned economy.
The complex was composed by:
- process units (ethylene, hydrogenated gasoline, low density
linear polyethylene, high density polyethylene, polypropylene,
poly butadiene, etc.),
- service units or utilities (power generation, steam generation,
cooling towers, etc.),
- piping interconnection and storage system,
- auxiliary buildings and civil works (roads, office building,
workshop, warehouses, canteen, gatehouse, etc.).
The project was studied to be completed in
different phases, in order that phase one could have been put in
operation while phase two was still under construction and phase three
still through the engineering process.
In order to have an idea about the magnitude of the
project, reference could be made to the following data:
- concrete: 370.000 m3 (cubic metres)
- electrical cables: 2060 km
- imported material: 145.000 Mg (tons)
- standard man-hours: 16.500.000 Smh
- actual man-hours: 28.000.000 Amh about
- construction time: 4 years (phases one and two)
- manpower on site: 6000 people (average), direct manpower 4500
people
- value of the construction works (1985-90): 900.000.000 ECU
2.2 Contractual organisation
At the beginning, the purpose of the Owner has been
to assign the whole of the project, engineering and construction, to a
major European General Contracting company; the bidding process,
however, was open also to U.S. and Japanese companies.
The first bidding process did not give any result:
at that time, no one of the General Contractors in the world was
willing to assume the whole responsibility of this project. To be
noted that, at that time, the political risk of the country was still
high.
The Owner decided to manage the works by itself,
assigning to various contractors the engineering and the construction
works, separately. In reality, the Owner's structure was able to
manage plants in operation, while they had no experience at all in
engineering and construction, so co-ordination problems started.
Initially those problems were due to discrepancies between engineering
of different companies.
The Owner then decided to put in charge a Project
Managing Contractor. They called a major engineering company with a
wide experience in general contracting of refineries and major
chemical and petrochemical complexes.
2.3 Parties involved
a. Owner
The Owner was actually a National Company, whose
scope was the management of one petrochemical complex already in
operation as well as of the complex under construction.
The National Companies were institutionally
organised as follows:
- The property was belonging to the State itself and was managed
through the Ministry of Industry, whose functions were the general
co-ordination as well as to appoint and recall the members of the
Boards of Directors of the Companies. The Ministry itself was
acting as the holding company, without an intermediate Holding
Corporation like happens in other countries.
- National Companies were actually acting as private companies,
under the laws governing the private system.
In the National Company under consideration the
Board of Directors was composed by 11 members, three of whom involved
in the project, namely:
- the Chairman & Managing Director who was actually a
politician without neither specific nor management experience,
- the Construction Executive Director with a wide professional
experience, he was actually the Project Director,
- the Planning Executive Director.
The National Company's Representative on site was a
top manager whose title was Construction Manager (note that this title
was not properly used). The functions belonging to the Owner were the
following:
- financial management of the project,
- representation in front of other Government bodies and
Authorities,
- management of the complex after its completion,
- purchase of local material,
- transportation of imported material from FOB (Country of Origin)
to Site,
- management of site warehouses,
- general site services (camp for workers, offices, power, etc.).
b. Project Managing Contractor (PMC)
The functions belonging to PMC were the following:
- Integrated Project Management, including
- general management of the project, with all powers to manage
the contracts with all the involved parties and without the
power of modifying those contracts,
- operating management of the construction contracts,
- planning, scheduling, progress monitoring and project control,
- cost control (limited to construction),
- co-ordination of head-office activities,
- management of site activities,
- co-ordination of site engineering,
- Training of the personnel of the Owner (administrative,
management).
- Assistance to the Owner in relationship with other Govt. Bodies
or Authorities.
c. Engineering Contractors or Process Units Contractors (PUC)
The functions belonging to PUC were:
- Process Engineering, Licenses, Technology.
- Engineering, purchase of material to be imported, transportation
to FOB.
- Technical supervision to site warehousing.
- Technical supervision to the construction works (to assure that
the works were executed as designed and engineered), site
engineering.
- Technical supervision to precommissioning and commissioning.
- Training of the personnel of the Owner (technical).
d. Construction contractors
Major national or international contractors with a
proper organisation, their task was construction, installation of the
imported material, precommissioning and commissiong of the
petrochemical plant properly so said. They were using its own manpower
and equipment, while construction material was given by the Owner.
e. Civil contractors
Minor local civil contractors whose task was
engineering and construction of the ancillary building, roads, fencing
works, etc.
3. Planning and project
control
Planning and project control were very
sophisticated, based on PMC's technologies, extremely advanced at that
time.
The planning and project control procedure
included:
- a master plan and a detailed scheduling,
- a weekly progress monitoring procedure and report,
- a monthly complete project control procedure and report,
- a monthly cost control procedure and report,
- updating of scheduling whenever needed.
The master plan was modified twice to cope with a
general delay from 48 to 66 months and once to cope with the decision
of starting the so called phase three.
4. Organisation of PMC
PMC was a major engineering and construction
company, whose scope was to act as consulting engineer and general
contractor, with several thousand employees.
The company was organised by functional departments
with co-ordination and integration offices (weak matrix organisation),
in detail:
- the Board of Directors was composed by 7 members,
- the Chairman was acting as Chairman of all companies belonging
to the same Group (so he was actually the Chairman of the
Group),
- the Vice Chairman & Managing Director was the real Chief
Executive of the company,
- directly under the Vice Chairman:
- Administration and Finance Dept. (accounting, bookkeeping,
treasury, finance),
- Human Resources and Organisation Dept.,
- Technology Dept. (technologies, patents, licences),
- the General Manager would have been correctly defined as
Operating Manager, since a lot of general management functions
were belonging to the Vice Chairman; under the General Manager,
- the Engineering Manager (project co-ordination, planning and
project control, engineering, purchase, marketing and proposal),
- the Construction Manager (site management),
- the organisation of every single project was composed by
- Project Manager (under the General Manager), with full power
of representation, regarding the project, towards external
parties, but without strong internal powers,
- Project Co-ordinator, (under the Engineering Manager), who was
the real governing authority of the project,
- Project Staff (project engineers, contract manager, business
manager, project comptroller),
- Site Manager (under the Construction Manager) and Site Staff
(construction manager, site engineers, etc.),
- in each country a Resident Manager (under the General Manager)
and his Staff were in charge for all local administration,
representation and legal problems.
It was actually the normal organisation structure
of a major engineering and construction company, with some
peculiarities. The weak points were not enough power given to
co-ordination and too much power given to Engineering and Construction
Areas. The consequences were a weak project management and a weak
general management , in reality the chief executive was the Vice
Chairman while the real general management was divided between the
Engineering and Construction Managers.
5. Organisation of the
Project
a. Project Managing Contractor
The Project Managing Contractor's project
organisation was as follows:
- Project Manager and Project Co-ordinator were the same person,
as a matter of fact this project was not considered as an
important one, if compared to general contracting, but as an
experimental project,
- Country Office: since the company had several contracts in
progress in the same country together with a continuous marketing
activity, there was a Resident Manager in the capital town
together with his Staff.
- the Site Manager was the real governing authority of the
project, at least locally; he was the manager accredited towards
the Owner. He was assisted by a Vice Site Manager. The Site
Organisation was composed by:
- the Office Manager and his staff (accounting, site
treasury, personnel, local general services),
- the Planning and Project Control Dept., composed by the
Planning & Project Control Manager, two Planning
Engineers, one Cost Engineer and four to five assistants,
- the Contract Administrator,
- the Site Engineering Manager,
- the Quality Assurance Manager,
- the Data Processing Dept. (mainframe on site),
- the Material Manager (transportation, warehouses),
- the Construction Manager, with a matrix construction
organisation formed by Area Managers and by functional
departments (civil, mechanical, electrical, instrumentation,
painting and insulation, precommissioning).
b. Engineering Contractors
Major or middle size engineering companies. The
head office engineering was organised in an independent matter and was
not under the effective control of the PMC. Locally their structure
was limited to the technical staff under the supervision of a Manager.
c. Construction Contractors
They were differently organised. The major between
them, whose contract was to make civil and installation works of five
process units plus four utilities, was organised with the following
scheme:
- the Site & Construction Manager, was the overall responsible
for all the activities as well as of the representation and legal
problems of the company towards the local Authorities, as well as
the full responsible for construction management; under him there
were
- the indirect functions for administrative, financial and legal
problems,
- the Planning Manager, who was also deputy of the Site Manager
with some general co-ordination functions,
- the Electrical and Instrumentation Section,
- the Painting and Insulation Section,
- to be noted that some works were sublet to Subcontractors,
creating some further problem and the need of a proper sub
organisation within the Mechanical and Electrical Sections.
d. Relationship between Owner and Project Managing Contractor
It is worthy to note that, between Owner and PMC,
there was a very complicated network of relationship. As a matter of
fact, since PMC was supposed to train the Owner's staff, people from
Owner's organisation were assigned, for this purpose, to different
PMC's offices or departments.
The relationship between these people, the chief of
PMC's office and the chief of Owner's corresponding office can be
summarised as follows:
- PMC had the full power to assign duties and to define the level
of discretionality for each person to work , to decide start and
stop of the various duties, to assign priorities and to check the
execution of such duties, while
- PMC had no power about selecting and deselecting people (only
limited powers to reject unsuitable persons), moving to an office
to another, job evaluation and careers, holidays.
Useless to say that the above could have been
improved, it was far from being perfect.
The relationships between two different
organisations due to cooperate or, like in this case, the injection of
key-personnel from one organisation into a second one, should be
carefully studied and contractually defined in detail.
In the case under study, the results were that
- organisation and project control were good, enough detailed and
reliable, it was possible to know every week the real progress
(planned versus actual) in several aggregated or disaggregated
forms, responsibilities for delays were clearly attributed to the
really responsible party, while
- delays could not be avoided nor kept under strict control; PMC
was able to suggest the proper corrective action but was not
enough strong to impose its implementation; the main reasons of
delay (transportation, construction manpower) were not actually
under PMC control.
At the bottom line, we could say that PMC was
really acting as a Project Monitoring Contractor.
7. Project Management and
Integrated Engineering
The following terminology starts to be accepted by
everyone:
ENGLISH |
ITALIAN |
SPANISH (castellano) |
Cost Engineering |
Ingegneria dei Costi |
Ingenieria de Costos |
Total Cost Management |
Ingegneria Economica |
Ingenieria Económica, Financiera y de Costos |
Project Financing |
Finanziamento di Progetto, Ingegneria Finanziaria |
Ingenieria Financiera |
Project Management |
Gestione di Progetto |
Ingenieria de Proyecto |
Engineering (overall, integrated) |
Ingegneria Integrata |
|
To be reminded that
- the term Project Director (in British terminology Project
Manager, lev. 5) identifies the person in charge for the main
decisions relevant to the project, including decisions relevant to
budget, contracts, major changes, suspensions, scope of works, he
is also a key-person in the initial decision, whether to go on
with the project or not, while
- the term Project Manager (in British terminology Project
Manager, lev. 4) identifies the person in charge to manage the
project, within assigned budget and contracts, with full power of
interference in the management of all the departments as well as
in the operations of contractors and subcontractors,
- the term Project Co-ordinator identifies a co-ordinator with
limited or without powers of interference.
The project management does not change if it is
done directly by the Owner, by the Owner through a PMC or by the
General Contractor:
- in the first case the Owner shall have the whole project
management staff, with the functions of planning, monitoring,
contracting etc., both Project Director and Project Manager shall
belong to Owner's organisation while engineering and construction
shall be done by the relevant contractors;
- in the second case the Owner' shall have only the Project
Director with a limited staff, while project management with all
the involved function shall be given to PMC people;
- in the third case all functions shall belong to the General
Contractor, who shall therefore have both Project Director and
Manager; the Owner shall have a Director in charge (Project
Director, Programme Director) with a limited staff and sometimes
shall rely on an external consultant and Project Monitoring or
Auditing Contractor in order to keep under control what the
General Contractor is doing.
When the project is made under full project
financing, the criteria do not change while the organisation could be
different. In these cases, in general, a proper project company
(special purpose vehicle) is formed, whose study is beyond the limits
of this paper.
dr. ing. Gianluca di Castri, FwAICE CCE/ICECA
Ingegnere Meccanico
Esperto in Ingegneria Economica
E-mail:
gdicastri@uli.it
6 March 2000
|